Wolseley Case Study

Wolseley UK’s Sure Touch


How To Reduce Supply Chain Costs Without Compromising Quality

Introduction

Supply chain director Derek Robb took up this post at Wolseley UK in April 2008, just as the first signs of global recession were being felt in European markets. Even then, Derek realised that the UK business, with sales of c£2.7bn, was in need of supply chain consolidation, given the slowdown in growth that the business had already forecast.

He said: “By early 2008, it was obvious that the business, which is best known for its Plumb Center, Build Center, Brandon Hire and Bathstore brands, needed to review its distribution infrastructure. The business had grown significantly in the early part of the decade and was set up to cope with a doubling in growth every five years. The landscape had changed significantly and we needed a new supply chain model.”

The Challenge

Given the fact that a major element of Wolseley’s infrastructure costs lay within the 17 distribution centres (DCs) he had inherited on arrival 3 years earlier, Robb turned to independent supply chain consultancy Total Logistics to undertake analysis on the impact of various network scenarios. The team at Total Logistics is well known in the sector for its sophisticated approach to supply chain modelling that enables sensitivity analysis to be undertaken to assess the impact of DCs being established or removed from specific locations.

Derek Robb said: “Using an external consultant with relevant experience was invaluable when it came to confirming our thoughts on the future shape of the supply chain model. The team at Total Logistics acted as a good sounding board, allowing us to undertake scenario planning on the options that we had in mind.”

The Solution

At the same time as the warehouse consolidation project, Wolseley’s supply chain team also looked at other cost saving initiatives such as reducing delivery frequency, outsourcing 3PL provision in Scotland and also exploring new supply chain options for the group’s Bathstore brand. Going back to basics and getting stock levels and inventory management right was another key element of the strategy.


The Results

In the final analysis, Wolseley UK’s proactive approach to supply chain management shows how insight and decisive action is vital to reduce costs, whilst not negatively impacting customer service levels.

Through a mixture of network rationalisation, the adoption of 3PL to establish a flexible cost structure and better inventory management, Wolseley was able to reduce its overall supply chain costs by 30 per cent.

 

Return to case studies page:

Click to download a pdf of this case study   supply chain logistics

 
Supply Chain Consultancy

Wolseley is the biggest name in plumbing and heating products in the UK. However, operating such a sizeable business brings real challenges when the construction industry is facing unprecedented falls in demand for products such as piping, radiators, taps, sinks and other sanitary ware.

 

Sign up for our e•newsletter

Our in-house newsletter provides useful information on current logistics and supply chain issues and company news.

Sign up for our e-newsletterFollow Total Logistics on Twitter

© Copyright 2006 - 2012 Reg. Office. Reg. in England and Wales | Co. Reg. No. 7189187 | VAT Reg. No. 537 552 236.  |  Privacy  |  Terms & Conditions  |  Sitemap  |  Search Engine Optimisation Kent  |  Online CMS